Difference between revisions of "Create and Schedule a Task"
(3 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
{| | {| | ||
− | | [[ | + | | [[TMS-VERSION 2|'''''>> Back To TMS-VERSION 2''''']] || [[Timeline (Gantt Chart)|'''''>> Timeline''''']] |
|} | |} | ||
− | + | =='''Follow the steps to create a new task in timeline page'''== | |
− | + | ||
− | + | ||
*TMS - In timeline page, we can create a task by right clicking on any task display “Add new task” | *TMS - In timeline page, we can create a task by right clicking on any task display “Add new task” | ||
Line 48: | Line 46: | ||
[[File:TMS325.PNG]] | [[File:TMS325.PNG]] | ||
+ | |||
+ | |||
+ | =='''Create / schedule task in timeline'''== | ||
+ | |||
+ | [[File:Create R schedule task in timeline.gif]] |
Latest revision as of 04:38, 13 April 2015
>> Back To TMS-VERSION 2 | >> Timeline |
Follow the steps to create a new task in timeline page
- TMS - In timeline page, we can create a task by right clicking on any task display “Add new task”
- Click on the folder in left pane
- Click on Timeline icon in top header
- Right click on any one of the task bar, display Add new task click on that to create a new task
- Task pop up gets display, then enter the task details
- To reschedule the task by Drag and drop a task bar to a new date to reschedule the task
- To update the task’s duration, hover the cursor over the task’ bar left or right border display circle icon and drag the bar to extend the task’s duration